top of page

Supreme Court Holds NOIDA Time Extension Charges Penal and Outside CIRP Costs in Granite Gate Insolvency

Writer: Kaustav Chowdhury
Kaustav Chowdhury
2 hours ago
5 min read

Background and Facts

The Supreme Court on September 6, 2026 held that time extension charges levied by a development authority for a developer's delay are penal in character and cannot be loaded into the insolvency resolution process costs of the corporate debtor. The judgment in The Authorised Representative for Granite Gate Properties Private Limited v. M/s New Okhla Industrial Development Authority and Others is reported as 2026 INSC 952.

Granite Gate Properties Private Limited developed two residential projects, Lotus Boulevard in Sector 100 and Lotus Panache in Sector 110, on land held from the New Okhla Industrial Development Authority (NOIDA) under perpetual lease. The projects were promised for completion in 2016. Delays ran beyond a decade, and the developer was admitted into the Corporate Insolvency Resolution Process, with the homebuyers constituting the Committee of Creditors as financial creditors in a class.

NOIDA sought to recover time extension charges accrued on account of the developer's failure to complete construction within the lease timelines. Because those charges related to the leasehold on which the projects stood, the question arose whether they should be treated as insolvency resolution process costs, payable in priority under Section 53(1)(a) and therefore borne in substance by the homebuyers and the successful resolution applicant.

Key Legal Issue

The issue was whether charges imposed as a consequence of the corporate debtor's own default before the insolvency commencement date can qualify as insolvency resolution process costs within Section 5(13) of the Insolvency and Bankruptcy Code, 2016, and whether a statutory development authority may insist on their recovery from homebuyers and an incoming resolution applicant who bore no responsibility for the delay.

The Supreme Court's Ruling

A bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran held that the time extension charges were penal in nature and could not be treated as CIRP costs. The Court directed that they be excluded from the resolution process costs and waived to the extent they were sought to be recovered from the homebuyers and the resolution applicant.

Penal Levies Do Not Become Process Costs

Section 5(13) defines insolvency resolution process costs to include the costs of running the corporate debtor as a going concern, amounts raised as interim finance, fees payable to the resolution professional, and other costs directly relating to the resolution process as specified by the Board. Regulation 31 of the IBBI (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 specifies the costs that qualify.

A charge that crystallises because the corporate debtor breached a construction timeline years before admission is not a cost of running the business during the resolution process. It is a consequence of pre-commencement default. Characterising it as a process cost would convert a penalty for past conduct into a priority payment under Section 53(1)(a), ranking ahead of the very creditors the default injured.

Homebuyers Cannot Be Made to Bear the Developer's Default

The Court's reasoning turns on who ultimately pays. In a real estate insolvency where homebuyers form the Committee of Creditors, any amount added to the process costs reduces the recovery available to those same homebuyers, or is passed to them through the resolution plan as an additional demand. The successful resolution applicant is in the same position: it prices its plan on the liabilities disclosed, and a penal levy for the previous management's delay is not a liability it caused.

Allowing recovery would mean that allottees who had already waited a decade for possession would pay a second time for the developer's failure to deliver.

The Welfare Character of a Development Authority

The Court addressed NOIDA's status directly, observing that the authority, though engaged in commercial ventures,

"cannot be divorced from the essential purpose which every local authority pursues, that is welfare measures without a mere profit motive".

A statutory development authority is not an ordinary commercial lessor. Where its lessee has collapsed into insolvency and the beneficiaries of the project are homebuyers, the authority's recovery of penal charges must yield to the statutory objective of reviving the project and delivering possession.

Practice Notes

In practice, the judgment reshapes how land-related dues are handled in real estate insolvencies:

  • For resolution professionals: Demands from development authorities should be disaggregated at the verification stage. Ground rent, lease rent and current charges accruing during the resolution process are capable of being CIRP costs. Penalties, time extension charges and delay levies referable to pre-commencement default are not, and should not be admitted into the process cost computation without an order.

  • For homebuyers and their authorised representative: Where an authority's claim is loaded into process costs, the authorised representative should challenge the characterisation rather than only the quantum. The distinction between a process cost and a penal claim determines whether the class pays in priority or not at all.

  • For resolution applicants: Plans for stalled real estate projects should expressly identify which authority demands are assumed and which are contested, and should seek a specific direction on penal levies at the Section 31 approval stage rather than leaving the question to post-approval recovery proceedings.

  • For development authorities: Recovery of delay-related charges from a corporate debtor in insolvency will be tested against the welfare purpose of the authority and the position of the allottees. Claims framed as compensation for a continuing statutory service stand on a different footing from claims that are penal in substance.

Key Provisions Discussed

  • Section 5(13) of the IBC: Definition of insolvency resolution process costs.

  • Section 30(2) of the IBC: Requirement that a resolution plan provide for payment of insolvency resolution process costs in priority.

  • Section 31 of the IBC: Approval of the resolution plan and its binding effect on all stakeholders, including statutory authorities.

  • Section 53(1)(a) of the IBC: Priority of insolvency resolution process costs and liquidation costs in the waterfall.

  • Regulation 31 of the CIRP Regulations, 2016: Costs specified as insolvency resolution process costs.

  • Section 5(8)(f) of the IBC: Treatment of amounts raised from allottees under a real estate project as financial debt.

Case Details

  • Case: The Authorised Representative for Granite Gate Properties Private Limited v. M/s New Okhla Industrial Development Authority and Others

  • Citation: 2026 INSC 952

  • Court: Supreme Court of India

  • Date of Judgment: September 6, 2026

  • Bench: Justice J.B. Pardiwala and Justice K. Vinod Chandran

  • Projects: Lotus Boulevard, Sector 100 and Lotus Panache, Sector 110, NOIDA

  • Outcome: Time extension charges held penal; excluded from CIRP costs and not recoverable from homebuyers or the successful resolution applicant.

Sources and References


Disclaimer: This article is for informational purposes only and does not constitute legal advice. Readers should consult a qualified legal professional for advice specific to their circumstances.

Comments


bottom of page